Basic and Executive Project
– Revamp of the Butadiene Units I and II and of the Boilers of the UNIB
– Chilled Water System
– Reutilization of the DMT Plant process Air Compressor
– Substitution of the Granulator and Installation of the Peccet Covering System in the PEBD Plant
– Substitution of the Satellite Extruder of Unit B
– Multidisciplinary Projects in the Units of Braskem – Small Projects
Executive Project
– Substitution of High, Medium and Low voltage Panels in Substations SE-11 and SE-31